FG to Close Nnamdi Azikiwe Int’l Airport for 6 Weeks

The Minister of State for Aviation, Senator Hadi Sirika, says the Nnamdi Azikiwe International Airport (NAIA), Abuja, will be closed for six weeks in February and March 2017 for total repairs on the runway.
Sirika told newsmen in Abuja on Monday that the closure was to allow Julius Berger carry out total re-construction on the badly damaged airport runway.
He said that while the runway would still be put to use under the six
months of rehabilitation, the six weeks would allow the midsection of
the runway to be reconstructed.
According to him, President Muhammadu Buhari has approved the reconstruction through the emergency procurement procedure for work to commence.
This, according to him, is because of the centrality, economy and the
importance of Abuja to the general administration of the country.
He said government could not afford to close down Abuja airport for a long time as palliative repairs had been ongoing at the runway in the last three months.
He said government could not afford to close down Abuja airport for a long time as palliative repairs had been ongoing at the runway in the last three months.
“From start to finish of the runway, it will take six months.
However, we will be using the runway almost throughout the period except
for about six weeks when the runway will be closed. That is when we are
going to do the midsection of the runway. The government has accepted
the design done by the contractor. The runway will last for than 10
years on completion early next year,’’ he said.
Sirika said Abuja bound passengers from any part of the world will
use Kaduna airport as alternative during the six weeks closure to
passengers.
He said arrangement had been finalised with Kaduna State, adding that
while the federal government will provide buses to convey the
passengers to Abuja, the state government will provide security.
According to him, it will cost government substantial amount of money
“but we think that palliative approach is wrong because three years
down we will come back to do the same repairs.
“Therefore, we decided to go for the bigger option which is to do
structural repairs if the runway which will take about six months to
complete,’’, he said.
On the Bilateral Air Agreement with other countries, Sirika said
government had signed BASA with 18 countries that Nigerians frequently
visit and do business with.
The MOUs, he said, would give Nigeria the opportunity to operate air services with 18 countries.
“With this, we have the freedom to fly and land safely in other air space and this will assist in opening our market.’’